Aerospace Projects
MET-CON, Inc.

 
Project: Boeing Evolved Expendable Launch Vehicle Mobile Service Tower
 
Owner: The Boeing Company

Architect: Raytheon Engineers and Constructors, Inc.

Contractor: Raytheon Constructors, Inc.

Contract Amount: $26,155,737

Completion Date: June 2002

Description: Construction of a new Mobile Service Tower for the Boeing Company's Evolved Expendable Launch Vehicle. Project is being constructed as a fast track project while the vehicle is under design. Work includes structural steel (approximately 4,000 tons), composite metal siding, fireproofing and coatings.

 
Project: Evolved Expendable Launch Vehicle Fixed Umbilical Tower

Owner: The Boeing Company

Architect: Raytheon Engineers and Constructors, Inc.

Contractor: Raytheon Constructors, Inc.

Contract Amount: $7,893,033.00

Completion Date: June 2002

Description: Construction of a new Fixed Umbilical Tower for the Boeing Company's Evolved Expendable Launch Vehicle. Project is being constructed as a fast track project while the vehicle is under design. Work includes structural steel (approximately 950 tons), composite metal siding and coatings.
 
Project: Vero Beach Airport Traffic Control Tower

Owner: The Federal Aviation Administration

Architect: Radian International LLC

Contractor: PCL Construction Services, Inc.

Contract Amount: $261,946

Completion Date: June 2002

Description: Structural and miscellaneous steel fabrication and erection of a 100 foot high air traffic control tower at the Vero Beach Municipal Airport.
 
Project: Replace Z Rails at Space Launch Complex 40 (SLC-40), Cape Canaveral Air Station, Florida
 

Contractor: Sunshine Construction and Engineering, Inc.

Engineer: AJT & Associates, Inc.

Description: Under this subcontract, Met-Con was tasked to remove and replace the support rails for the Mobile Service Tower at SLC-40. Duties included surveying the existing rails, demolishing them, setting the new anchor bolts, securing them against movement while foundations were poured, placing the leveling plates, and laying out and setting the new rails, all to a tolerance of three decimal places. A unique system of leveling bolts was installed to give the client the flexibility of later raising the leveling plates to compensate for anticipated settling of the rails. The work was accomplished using multiple shifts working 24 hours a day, 7 days a week. The project was completed ahead of schedule and in less than 60 days, resulting in early completion bonuses for both Sunshine and Met-Con.
 
Project: Movable Platforms, Centaur Processing Facility, Cape Canaveral Air Station, Florida

Contractor: David Boland, Inc.

Engineer: Reynolds, Smith & Hills, Inc.

Description: Under this subcontract, Met-Con was responsible for the detailing, machining, fabrication, erection, testing, and checkout of all fixed and movable platforms in this new $30M facility designed to support the processing of the Atlas-Centaur launch vehicle.

 
Project: White Room Extensions at Space Launch Complexes (SLCs) 17A & B, Cape Canaveral Air Station, FL

Contractor: Butler Construction Company, Inc.

Engineer: Briel, Rhame, Poynter & Houser, Inc.

Description: As principal subcontractor (85 percent of contract value) for the project, Met-Con was responsible for structurally reinforcing the existing Mobile Service Tower and Fixed Umbilical Tower on both complexes; removing the existing sliding roofs and hammerhead cranes; extending the existing white rooms vertically by 20 feet, including all doors with pneumatic seals and hydraulic operators; and reinstalling the original sliding roofs and cranes.

 

Top

 
     
Met-Con, Inc.
P.O. Box 236129
Cocoa, FL 32923-6129 USA
Shipping Address:
465 Canaveral Groves Boulevard
Cocoa, Florida 32926
Phone: (321) 632-4880
Fax: (321) 639-0158
email: krd@metconinc.com
 

Last Update August 06, 2008

 

Web Services by Ron Castle Webs

Site Map